Your pump’s Mean Time Between Repairs (MTBR) is what?…Or what should it be…

Your pump’s Mean Time Between Repairs (MTBR) is what?…Or what should it be…

pump_maintenance.jpg

Many of the tourist spots around the world have panhandlers. Some of the more creative ones stand on street corners advertising that they will tell you where you got your shoes, for a dollar. Of course it turns out that “you got your shoes” at the corner of Bourbon and St. Peters – or wherever you happen to be standing at the moment. It’s a play on words.

However, being able to predict your pump Mean Time Between Repairs (MTBR) is not a play on words. Indeed it can be done quite accurately. I am often asked to do a facility rotating equipment reliability audit. After all, the plant’s management has heard that top tier plants have pump MTBR’s in excess of 100 months. They would be happy to have half that number. Hence the need to understand the major MTBR influencing factors.

The main broad reliability categories that determine what the eventual, or as installed pump MRBR will be include:

  • Design (Process and Mechanical)
  • Operation
  • Maintenance

Besides these hard equipment categories we also have soft factors, such as management practices. These would include reliability, leadership, stewardship, and quality improvement programs. A comprehensive evaluation and development of corrective recommendations can often be a lengthy process, but quite necessary if we are serious about exceeding MTBR of 100 Months.  For simplicity, only a few select management practices are included in this MTBR estimator.

The first evaluation step is to look at the equipment and its operating conditions. Some hardware will never be reliable and some services are just plain difficult to work with. The best you may be able to do is to mitigate the bad process hand that you have been dealt. (For mitigating ideas I suggest one of the many excellent Heinz Bloch articles on Equipment Reliability Enhancements with Payback)

So let’s start with a hypothetical pump and a predicted MTBR of 100 months. Then let’s estimate what your actual MTBR is by applying derating factors.  For pumps, these factors  mainly involve the predominant seal and bearings problems.

Note that some are not direct causal factors and a few are interdependent. Many factors can be mitigated by minor hardware modifications, additional protective instrumentation and setting acceptable process operating limits. On the other hand just having a Vibration Program or Operating Envelopes will not do anything for you if they are not implemented well.

 

PUMP Estimated MTBR (months) = 100 x All Correction Factors

ITEM FACTOR LIST NORMAL If not normal use this
correction factor
ADJUSTED
PROCESS DESIGN

GPM
HEAD
PH
S.G.
TEMP
CONTAMINANTS
(any of the following)

FLUID single component
FLUID VISCOSITY

 
>100
<500FT
7 TO 9 PH
0.7 TO 1.0
0 TO 300
<3% BY WT
<.01″ SIZE
SOFT/nonabrasive
Non Crystallizing
Non solidyfying
Mixture

.95
.95
.85
.8
.9
.7

.9
.8

MECHANICAL DESIGN
CONSTRUCTION~API 610 like 
IMPELLER diameter
IMPELLER multistage
NSS     Suction Specific Speed
RPM
BEARINGS Ball
BEARING DN Id+Od(mm)/2*Rpm
BEARING housing liquid cool
BEARING seals/isolators
SHAFT Shaft Stiffness L3/D4
SEAL cartridge construction
SEAL PT margin adequate
  Sbox press > 1.3x VapPress @Ptemp or Tmargin of 36°F above Psb (see API 682)

Yes
<=.95 max
No
<12,000
<=1,800
No
<300,00
No
Yes
<50
Yes
Yes

.8
.95
.9
.8
.9
.95
.7
.8
.8
.7
.9
.5

 

OPERATION
FLOW >25% of time Below FrasierMin
NPSH Margin   @Q normal
SWAPPING (w/spare)1
Suction Strainers
Parallel Operation
Operating Envelopes Followed

No
>2ft
>=quarterly
No, or instrumented
No, or individual flow meters
Yes

.5
.9
.9
.7
.8
.6

 

MAINTENANCE
Predictive/Preventative Program
Vibration Monitoring Program
Acceptable radial vibration
Acceptable axial vibration
LUBE program and/or have oil mist

Yes
Yes
<.3ips
<.15ips
Yes

.8
.8
.8
.8
.8


1
Swapping a pump too often without a valid reason may result in an “infant mortality” failure. Swapping should be based on a justified need. Pump that is shut down should be properly prepared, for example when the pumped fluid may solidify; the case should be drained and refilled with a compatible non-solidifying fluid.

So there you have it. The “educated crystal ball” says that based on these parameters, the estimated MTBR may be even below 20 months. Surprised? Armed with understanding WHY it may be so low is a start to making it a lot better. Fleet leaders are now starting with a baseline MTBR of 150.

  Major MTBR Influence Areas  
< 50 months Hardware
50-100 Months Operation and Maintenance
>100 Months Management Practices

 

Let’s review some of the big impact items on the pump MTBR:

  1. Stay above the minimum (Fraser) flow
  2. Follow other design operating envelopes
  3. Assure that the seal is operating with an adequate PT margin

If your engineering staff dedicated to reliability improvements is limited, you can always supplement it with contractor support.  Also, as seal problems tend to cause most low MTBR issues, call on your seal supplier – all of the majors have excellent engineering, and quite often will issue recommendations for free.

Finally, management should exercise caution when comparing pump MTBR between various industries, plants, or even units. As can be seen above, the degree of granularity to make a valid ‘apples to apples’ comparison is quite involved.  Implementing a Bad Actor program and tracking improvements is often a good start on the road to improvement.

You may view similar Becht articles in our Rotating  Machinery section of Services – Click Here to View

|

About The Author

Contact:
Chris Zielewski retired recently from ExxonMobil where he last worked as a Machinery Section Group Leader. He has over 35 years machinery engineering experience with pumps, compressors, turbines and other petrochemical equipment. Chris served on the Texas A&M Turbomachinery Advisory Panel, and currently is an executive committee member of the Gulf South Rotating Machinery Symposium. His specialty areas include machinery reliability improvements and incident investigations. Chris holds a B.S. degree in Mechanical Engineering from Rutgers University, New Brunswick, New Jersey.