Case Study – Vibration of Gas Plant Piping

Case Study – Vibration of Gas Plant Piping

Piping vibration

Situation: International onshore gas plant receiving station was experiencing severe vibration which was limiting throughput.

Information: Becht sketched a reinforcement scheme while onsite.

Action Taken: Becht identified that the structure supporting the piping did not have proper bracing in the direction of motion.

Results: The addition of reinforcement to the structure eliminated excessive motion and allowed for full throughput performance.