Case Study – Strategic Investment Rationalization A North American refinery was experiencing significant crude quality change. They were losing access... Read More
Case Study – Incident Review/Best Practice Implementation A client had no formal incident analysis for an upcoming project. The Becht team reviewed several... Read More
Case Study – Logistics Management A US Gulf Coast client was limited in tankage and blending systems. Their target was to improve site... Read More
Case Study – Maintenance Planning: Alaska North Slope Situation: Becht was awarded a self-managed, multi-year contract for Maintenance Plann... Read More
Case Study – Seismic Rehabilitation for Piping Systems Situation: A gas separations facility experienced a large earthquake which damaged piping systems. ... Read More
Case Study – Fiber Wrapped Piping Situation: A client found leaking fiber wrapped piping on an offshore platform. Information: Bech... Read More
Case Study – FFS Level 3 Analysis Situation: Offshore rig had a surge tank which suffered an overpressure event and experienced signif... Read More
Case Study – Turnaround (TA) Planning & Execution Situation: Turnaround planning and execution at Alaska North Slope Central Compressor Plant. Turnaro... Read More
Case Study – Equipment Reliability Plans (ERPs) Development Situation: Developed Equipment Reliability Plans (ERPs) for an $8 billion (USD) offshore platform in... Read More
Case Study – Vibration of Gas Plant Piping Situation: International onshore gas plant receiving station was experiencing severe vibrati... Read More
Case Study – Weekly Level 1-2 FFS/Repairs Becht handles weekly FFS evaluations for the past 8+ years for an onshore facility in Iraq. If FFS f... Read More
RealWear Assists in Repairing Coke Drums Situation: Becht was awarded a project to perform a “Repair versus Replace” analysis of failing ... Read More
Case Study – Coker Heater TMT Assessment / Debottlenecking Of Rate To Capture Margin Situation: Delayed coker heater was the rate limiting component for a fuels refinery due t... Read More
Case Study – Vessel and Tank Rating Calculations for Midstream Tanks and Vessels Situation: 85 tanks and pressure vessels lacked complete design and operating inform... Read More
NHT High Organic Chloride A USGC refinery had been suffering for some time with high levels of organic chlorides in the naphth... Read More